Publications
-
Construction: An unwarranted contestation may be considered an abuse of procedure
In the decision in 9058-4004 Québec inc. c. 9337-9907 Québec inc.1 rendered on October 21, 2022, the court granted compensation to a subcontractor for its extrajudicial fees further to a general contractor’s unfounded contestation of its claim as part of a hypothecary action. The facts In (…)
-
Bill 37: What changes can be expected for Public Contracts?
On September 18, 2019, the Minister Responsible for Government Administration and Chair of the Conseil du trésor introduced Bill 37, An Act mainly to establish the Centre d’acquisitions gouvernementales et Infrastructures technologiques Québec1 As its name suggests, this bill is intended to (…)
-
How subcontractors or materials supplier can use the surety bond contract
That is what material suppliers want to know when general contractors with which they have contracted default on payment, particularly in bankruptcy cases. It is common practice for clients to require that the general contractor provide a surety bond to cover a significant breach of this nature. (…)
-
The City of Montreal revises its by-law on contract management
Redefining and expanding the concept of conflict of interest, clarifying situations of “ineligibility to contract”, introducing a principle of supplier rotation, increasing the eligibility threshold for the award of a private contract. These are the main changes that the City of Montreal has made to (…)
-
Builders’ Risk Insurance: Interpreting the Usual Faulty Workmanship and “LEG” Exclusions in connection with Ledcor and Acciona
Ledcor The issue in Ledcor1 was whether the builder’s risk policy taken out by the contractor that was contractually responsible for cleaning the windows of a building, covered damage to the windows caused by its poor cleaning work. The financial impact was significant since the cost of re-doing (…)
-
Caron confirms that employers have a duty to accommodate workers with an employment injury
On February 1, 2018, the Supreme Court of Canada rendered an important decision in Commission des normes, de l’équité, de la santé et de la sécurité du travail (“CNESST”) v. Caron1 (“Caron”), confirming the position expressed by the Court of Appeal in 20152 as well as the state of the law regarding (…)
-
Bill 162: An Act to amend the Building Act and other legislative provisions mainly to give effect to certain Charbonneau Commission recommendations
Tabled on December 1, 2017 by Lise Thériault, the Minister responsible for Consumer Protection and Housing, the main purpose of Bill 162 is to give effect to certain recommendations contained in the final report of the Commission of inquiry on the awarding and management of public contracts in the (…)
-
New developments regarding the criminal negligence of employers
On August 31, 2017, the Ontario Court of Justice sentenced1 Detour Gold Corporation (“Detour Gold”) to pay a fine of $2,625,333 after it pleaded guilty to a charge of criminal negligence causing the death of an employee. Facts Detour Gold has operated an open pit mine near the Ontario-Québec (…)
-
Legislative amendments regarding conservation of wetlands and bodies of water: troubled waters for developers?
Bill 132 respecting the conservation of wetlands and bodies of water, passed unanimously by the National Assembly on June 16th of this year, is in keeping with the context of a significant modernization of environmental laws in Québec. Most of its provisions come into force immediately. Described (…)
-
Latest developments in the Canadian infrastructure market / The Canada-Europe Free Trade Agreement: impacts on the infrastructure industry / Biomethanization: a fast-growing market in Québec
TABLE OF CONTENTS Latest developments in the Canadian market Fengate acquires a solar project portfolio from Canadian Solar TerraForm Power increases the financing of its Canadian solar power portfolio SaskPower launches a call for tenders for 200 MW of wind energy Boralex closes the (…)
-
A bid’s nonconformity to the eligibility criteria set out in a call for tenders, such as minimum experience, constitutes a major irregularity
When it comes to presenting a bid in response to a call for tenders made by a public body, two major questions are of interest to businesses concerned, namely “What is the nature of the contract?” and “Does my business conform to the conditions of the call for tenders, for example, those concerning (…)
-
A bid’s nonconformity to the eligibility criteria set out in a call for tenders, such as minimum experience, constitutes a major irregularity
When it comes to presenting a bid in response to a call for tenders made by a public body, two major questions are of interest to businesses concerned, namely “What is the nature of the contract?” and “Does my business conform to the conditions of the call for tenders, for example, those concerning (…)
-
The Role of the Expert under the new Code of Civil Procedure
The coming into force of the new Code of Civil Procedure on January 1, 2016 created some uncertainty for litigation lawyers. One issue was the role of experts in litigation and in particular the emphasis on joint experts and the filing of an expert’s report in lieu of testimony. Other provisions (…)